You can switch fire door manufacturers during a project without requiring a full new compliance assessment, but only if the replacement product carries an equivalent or superior fire resistance classification, covers the specified opening dimensions within its tested and extended application range, and is supported by complete CE documentation and an Efectis classification report. The critical question is not whether the manufacturer changes, but whether the replacement door system can be proven to meet the same specification the original selection was built on. The sections below address the specific conditions, documentation requirements, and approval steps that determine whether a substitution is compliant.
What determines whether two fire doors from different manufacturers are truly equivalent?
Two fire-resistant industrial doors from different manufacturers are truly equivalent when they carry the same fire resistance classification under EN 13501-2, cover the required opening dimensions within their respective tested and extended application ranges, and are both supported by valid CE documentation and independent classification reports. Classification alone is not sufficient: the tested configuration and dimensional scope must also align.
Fire resistance classifications under EN 13501-2 describe precisely how a door performs: the E criterion confirms that flames and hot gases are stopped; the W criterion limits radiant heat transfer and represents the Dutch standard baseline; and the I criterion addresses temperature rise on the unexposed side, with EI1 applying a stricter limit and EI2 permitting a higher temperature rise. A door classified EI1-60 and one classified EI2-60 are not equivalent, despite sharing the same duration: the insulation criterion differs in a way that affects both performance and downstream design decisions. Any comparison between products must account for this distinction explicitly.
Beyond classification, the extended application rules under EN 15269 determine which untested configurations a classification report legitimately covers. A door tested at a specific size and configuration can be applied to other dimensions only within the limits defined by its EXAP range. If the specified opening falls outside that range, the classification cannot be applied, and the products cannot be treated as equivalent for that opening regardless of the classification code they share.
Architects and specifiers comparing products from different manufacturers should request the full classification report, not just the CE certificate, from each manufacturer. The classification report, issued by an accredited fire-testing laboratory such as Efectis, specifies the exact test conditions, configurations, and dimensional limits under which the classification was achieved. This is the document that allows a genuine like-for-like comparison, and it is the document that closes a specification file with defensible evidence.
Need advice for your project?
Discuss your requirements for fire-rated doors, burglar-resistant roller shutters or a suitable solution with Metacon-Next.
Does switching manufacturers always require a new compliance assessment?
Switching fire door manufacturers does not automatically require a new compliance assessment, but it does require a structured equivalence review. If the replacement product carries the same classification, covers the specified dimensions within its EXAP range, and is supported by complete CE documentation and a valid classification report, the substitution can often be confirmed without commissioning new testing. The review process is the assessment. It is not optional.
The distinction matters because a compliance assessment in the context of a manufacturer switch is not necessarily a new fire test. What it is, at minimum, is a documented comparison of the original specification against the replacement product’s tested performance, dimensional coverage, and certification status. The outcome of that review determines whether the switch is straightforward or whether it creates a gap that must be resolved before the substitution is accepted.
A new assessment is likely to be required, or the substitution should be treated with particular caution, when any of the following apply:
- The replacement product carries a lower classification than the original specification (for example, EI2-60 replacing a specified EI1-60)
- The required opening dimensions fall outside the replacement product’s EXAP range
- The original specification was written around a specific tested configuration that the replacement product has not been tested in
- The project involves sector-specific regulation such as PGS15, where a qualified fire safety engineer or the competent authority may need to confirm that the substitute meets the applicable requirement
In all cases, the decision on whether a substitution is compliant rests on the specific project’s fire safety design, not on a general rule about manufacturer changes. A qualified fire safety engineer should be involved wherever there is any ambiguity about whether the replacement product satisfies the project’s compartmentalisation requirements.
What documentation must the replacement manufacturer provide before the switch is confirmed?
Before a fire door manufacturer substitution is confirmed, the replacement manufacturer must provide the CE declaration of performance, the underlying classification report from an accredited testing laboratory, and technical drawings that match the specified classification and configuration. These three documents together form the minimum evidence base for confirming that the replacement product meets the original specification.
CE declaration of performance
The CE declaration of performance is the manufacturer’s formal declaration of the product’s performance characteristics under the EU Construction Products Regulation. For industrial fire-resistant doors, CE marking is mandatory for market access in the EU and must comply with both EN 16034, which covers the fire-resisting closing function, and EN 13241, which applies to industrial doors generally. These two standards apply simultaneously and are not interchangeable. A CE certificate referencing only one of the two standards is incomplete for an industrial fire door.
Classification report
The classification report is the technical document that substantiates the CE declaration. It contains the actual fire test results and the classification derived from those results, including the specific dimensions, configurations, and hardware conditions under which the classification was achieved. It also defines the extended application limits, the EXAP range, within which the classification can be applied to untested configurations. This is the document that architects need at the specification stage to confirm that the replacement product genuinely covers the required opening. Requesting this document only after commitment to a product is a risk that can create late-stage compliance gaps.
Technical drawings matching the classification
A fire-rated door is a tested, certified system. The technical drawings used in a specification must correspond to the classification stated in the documentation. A generic drawing applied across multiple classifications is not acceptable: the drawing must reflect the actual tested assembly. If the replacement manufacturer cannot supply drawings that match the classification report, the specification cannot be closed with confidence.
Manufacturers who make this documentation available at the specification stage, rather than requiring it to be requested after order placement, allow architects and project teams to complete the equivalence review before the substitution is committed. Metacon-Next’s certified product range is supported by CE certificates, Efectis classification reports, and technical documentation that are available for review during the specification process, which is precisely when they are needed.
Who has authority to approve a manufacturer substitution on a fire-rated opening?
Authority to approve a fire door manufacturer substitution sits with the specifying architect, the fire safety engineer, and in some cases the competent authority or building inspector, depending on the project stage and the nature of the change. No single party holds universal approval authority; the appropriate sign-off depends on how the substitution affects the fire strategy and whether it requires regulatory confirmation.
The specifying architect carries responsibility for the fire compartmentation strategy as documented in the design. A manufacturer substitution that changes the product’s classification, dimensional coverage, or tested configuration is a specification change, not a like-for-like swap, and the architect must evaluate whether the revised specification remains consistent with the fire strategy. Where the architect is not also the fire safety engineer, the fire safety engineer should confirm that the replacement product satisfies the compartmentalisation requirements as calculated for the project.
Where the project is subject to a permit that references specific product documentation, or where the building inspector has reviewed the original specification, a substitution may need to be notified to the competent authority. This is particularly relevant where the change involves a different classification level or where sector-specific regulations such as PGS15 apply, since those regulations may impose requirements that go beyond the regulatory baseline and require confirmation from a qualified specialist.
Contractors and procurement teams do not hold authority to approve a manufacturer substitution unilaterally. A substitution that is commercially convenient but technically unreviewed creates liability exposure for everyone involved in the project. The approval chain should be documented, and the replacement manufacturer’s documentation should be on file before installation proceeds.
Need advice for your project?
Discuss your requirements for fire-rated doors, burglar-resistant roller shutters or a suitable solution with Metacon-Next.
What are the most common compliance risks when changing fire door suppliers mid-project?
The most common compliance risks when changing fire door suppliers mid-project are classification mismatches, EXAP range gaps, incomplete documentation, and system integrity failures caused by substituting components outside their tested configuration. Each of these risks is avoidable with a structured equivalence review conducted before the substitution is confirmed.
Classification mismatches
A classification mismatch occurs when the replacement product carries a different classification than the original specification, most commonly when EI1 and EI2 are treated as interchangeable, or when a lower duration is accepted as equivalent to a higher one. EI1 applies a stricter temperature rise limit on the unexposed face than EI2; replacing an EI1-specified door with an EI2 product is a performance downgrade, regardless of whether the duration is the same. This distinction must be verified explicitly during the equivalence review, not assumed from the classification code alone.
EXAP range gaps
Extended application rules under EN 15269 define the dimensional and configurational limits within which a tested classification can be applied to untested door assemblies. If the required opening falls outside the replacement product’s EXAP range, the stated classification cannot be applied to that opening, and the door cannot be installed as a compliant fire-rated assembly at that location. This is a common mid-project discovery when a supplier change is made without first verifying the replacement product’s dimensional coverage against the project’s actual opening sizes.
Incomplete documentation packages
A manufacturer substitution that proceeds without the full documentation package, CE declaration of performance, classification report, and matching technical drawings, leaves the project without the evidence base needed to close a permit file or respond to a building inspector’s query. Documentation gaps discovered after installation are significantly more costly to resolve than those identified during the specification review. Requesting a full documentation package before committing to a replacement product is the straightforward way to avoid this risk.
System integrity failures
A fire door classification covers a tested system (door leaf, frame, hardware, seals, and installation configuration), not individual components in isolation. Substituting a door leaf from a different manufacturer while retaining the original frame, or using hardware not covered by the replacement product’s classification report, can invalidate the classification even if the door itself carries the correct CE marking. The replacement product’s classification report must be reviewed to confirm that the complete assembly as it will be installed on site falls within the tested and documented scope.
Avoiding these risks requires treating a mid-project supplier change with the same rigour as the original specification decision. The Metacon-Next technical team can support architects and project teams in reviewing whether a substitution is technically sound, including confirming classification coverage, EXAP limits, and documentation completeness for the specific openings in question. When passive fire protection compliance must be provable at every stage of a project, the documentation behind a manufacturer substitution is not a formality: it is the compliance record.
For projects where fire-rated industrial openings must combine certified performance with operational requirements such as forklift access, high-frequency use, or large clear widths, Metacon-Next’s fire-rated industrial door range provides the tested, CE-certified product documentation that allows architects to specify with precision and defend those choices throughout the project lifecycle. Every product in the range is supported by Efectis classification reports and CE documentation available at the specification stage, the point in the process where they are most useful, whether for an original specification or a mid-project substitution review. More information about the full product range and available certifications is available at metacon-next.com/en/products/.